Supply, installation, testing and commissioning of Air Handling Units in Bank’s Office Building, Kanpur.
Tender number | Public Ten |
Date of publication of NIT | Mar 29, 2009 |
Nature of work | Supply, installation, testing and commissioning of Air Handling Units in Bank’s Office Building, Kanpur. |
Mode of tender enquiry | Press Advertisement |
Type of bidding (single/two bid system) | 2 |
Last date of receipt of tender | Apr 30, 2009 |
Number of tenders received | Three |
Nos. and names of parties qualified after technical evaluation | Three 1. M/s ETA Engineering Pvt.Ltd. Noida, 2. M/s Kalyan Kooling Corporation, Kanpur, 3. M/s Skyline A. C. Engineering Pvt. Ltd. New Delhi. |
Nos. and names of parties not qualified after technical evaluation | NIL NIL |
Commercial Bid Ranking, if any | |
Final Ranking, if any | |
Whether contract awarded to lowest tenderer/evaluated L1 | Yes |
Contract number and date | Kan. Sampada/1804/03.01.056/2009-10 Nov 27, 2009 |
Name of contractor | M/s Skyline A. C. Engineering Pvt. Ltd. New Delhi. |
Value of contract | Rs. 21,26,425/- |
Scheduled date of completion of supplies | Feb 21, 2010 |
Actual date of start of work | Jan 26, 2010 |
Actual date of completion of work | Apr 18, 2011 |
Reasons for delay, if any | The Firm completed the work on April 14, 2010 but during operation it was felt that there is some problem in the belts and pullies of A.H.Us. Firm repeatedly tried to rectify the defects and the same were finally rectified on April 18, 2011. |